It’s Bond Season and Sweater Weather! (Part 1)

Designing Excellent, Efficient, and Equitable Educational Spaces

As bond season approaches, we know it takes intricate coordination to keep these projects running smoothly—budgets, schedules, design, construction, safety, scopes, changes orders, user and public input, legislation, and more. So, grab yourself a latte, get cozy, and we’ll tell you a story about how Process can assist you with designing excellent, efficient, and equitable educational spaces economically.

On-time and Budget

Every proposal will use this language and every architect means it. But what we rarely talk about in depth are the strategies we use to achieve this. Tracking schedules and costs are a given—but there are numerous considerations that can be addressed in the pre-design and design phases to reduce and even eliminate challenges during construction.

Schedule delays can show up in many forms and are one of the costliest aspects of a project. Strong leadership requires a team that thinks about the entire process from the get-go and takes into consideration everything that may impact the success of a project.

This requires precision. The Process team implements a thoughtful and strategic approach to all the conditions that influence a project’s success. We ask questions not solely around the design of spaces, but of how we will deliver these spaces. Those questions will help us with:

  • Understanding funding streams (loans, grants, donors, etc.) and when more resilient and/or expensive up-front costs offset operations costs.
  • Understanding construction on occupied campuses above and beyond safety and how it can influence design decisions and product selections.
  • Assisting with preparing a cost benefit analysis of various bid strategies.

For this two-part series, we will first discuss funding streams and when more resilient and/or expensive up-front costs offset operations costs.

Funding Strategies

Funding Strategies High Schools Process Architecture

When a community passes a school bond, they are trusting the district to stretch every dollar. But with aging infrastructure and growing deferred maintenance lists, those funds can disappear quickly.

That’s why, in today’s landscape, school design and financial strategy must go hand in hand.

At Process, we believe exceptional K-12 architecture isn’t just about beautiful spaces—it’s about fiscal stewardship. When tackling deferred maintenance, we design with your funding pathways in mind from project start to completion. The result? Projects that maximize value AND design.

  • Layering Energy Trust of Oregon Incentives: From upgrading complex HVAC systems and building envelopes to modernizing lighting, we design systems that trigger cash incentives to offset capital costs.
  • Lowering Operational Costs: The best way to respect a bond is to ensure the resulting buildings cost less to run. Our design process targets long-term utility savings, redirecting precious dollars back into the classroom.

We also understand and integrate additional funding sources like the Perkins funds for CTE (career-technical education) equipment, NSLP (National School Lunch Program) for cafeteria renovations, SRGP (Seismic Rehabilitation Grant Program) for retrofitting, and donor contributions.

Hillsboro High School – Case Study

Hillsboro High School Bioscience Process Architecture

At Hillsboro High School, Jason Karam and Nick Turrell designed a bond-funded bioscience lab while equipment purchases were supported through CTE Revitalization Grants. Although the specific equipment had not been selected during the design phase, our team planned for future needs by coordinating anticipated power and water requirements and even increasing the prep room door size to accommodate larger equipment.

By thinking beyond the immediate scope, the team created a flexible lab that could support future equipment purchases without requiring costly or disruptive renovations later. We recognize that not every detail will be known during design, but that does not prevent our team from planning for future equipment, evolving programs, and preparing for long-term needs.

Hilhi’s Bioscience CTE Pathway was recognized in the March/April 2026 edition of Oregon Life Science’s Bio Bulletin as one of the oldest and most successful high school biotechnology programs in Oregon.

In addition to understanding how these combinations of funding can enhance a project to allow more bang for your buck, it’s equally important to understand when there are “strings attached” to various funds. Having this knowledge at the ready influences the design strategy and helps avoid design conflicts later in a project’s lifecycle.

MORE INFO ON HILHI’S BIOSCIENCE PROGRAM

Spending More to Save More – Avoiding Redoes

While we’re talking about money, it’s important to mention resiliency and operational efficiencies vs costs. Being a good steward means balancing the various funding pathways with future-proofing educational facilities. Obviously, we want to select durable furniture, fixtures, and materials and consider changes in technology and equipment as mentioned in the Hillsboro High School example. But there are more complex issues that can arise.

Jason and Nick once assisted with a redesign of Glencoe Elementary School’s parking lot because student dropoff and pickup was so congested, they had to assign an operations employee as a flagger. The cost of the redesign offset the unproductive expenditure of paying staff to keep the parking lot safe. We do our clients and projects a great service by considering these scenarios before projects are complete so that redesigns don’t become necessary. We ask how every space and area of a school is being used, who the users are, and when they are using them.

The roof replacement at Nellie Muir Elementary School in Woodburn is an excellent example of making hard decisions now to save money later—a lot of money.

Nellie Muir Elementary Roof Process Architecture

Nellie Muir’s existing flat roof required a membrane replacement. While we were at it, it made sense to do a seismic upgrade as well. That led us to discovering that the insulation wasn’t up to code. When we got further into it, we realized the roof wasn’t draining properly either. We needed to add roof drains and positive slopes to the scope or the new 30-year roof would turn into a 15-year roof. We call these changes value-added because it’s much easier to accept them when we know they will provide peace of mind and safety.

coffee

Have you finished your latte and then some? We hope you’ve found this helpful and appreciate your interest!

Check out Part 2, where we will cover the complexities of design on occupied campuses and analyze alternate delivery methods.